Supreme Court limits scope of NEPA law that has been used to endlessly delay infrastructure projects

Supreme Court limits scope of NEPA law that has been used to endlessly delay infrastructure projects
U.S. Supreme Court

“The US Supreme Court has limited the scope of the National Environmental Policy Act (NEPA), ruling that federal agencies are not required to consider indirect environmental effects when evaluating projects. The ruling is expected to streamline federal approvals for infrastructure projects, reducing litigation risks and fostering a more efficient regulatory environment,” reports The Doomslayer.

Law professor Jonathan Adler explains that on May 29,

the Supreme Court decided Seven County Infrastructure Coalition v. Eagle County, which challenged the U.S. Court of Appeals for the D.C. Circuit’s capacious understanding of agency obligations under the National Environmental Policy Act. The justices unanimously rejected the D.C. Circuit’s approach, but split 5-3 over what the D.C. Circuit did wrong. Justice Kavanaugh wrote for the Court, joined by the Chief Justice and the Court’s conservative justices (other than Justice Gorsuch, who was recused). Justice Sotomayor wrote an opinion concurring in the judgment, joined by Justices Kagan and Jackson….the biggest significance of this opinion is that it clarifies that NEPA does not require Environmental Impact Statements to consider upstream and downstream effects of projects that are caused by third-parties. This is particularly significant for infrastructure projects, such as pipelines or transmission lines, and should help reduce NEPA’s burdens (at least at the margins). The opinion will also likely hamper any future efforts, perhaps by Democratic administrations, to expand or restore more fulsome (and burdensome) NEPA requirements.

As the Supreme Court explained in its opinion:

Some 55 years ago, Congress passed and President Nixon signed the National Environmental Policy Act, known as NEPA. For certain infrastructure projects that are built, funded, or approved by the Federal Government, NEPA requires federal agencies to prepare an environmental impact statement, or EIS. The EIS must address the significant environmental effects of a proposed project and identify feasible alternatives that could mitigate those effects.

NEPA was the first of several landmark environmental laws enacted by Congress in the 1970s. Subsequent statutes included the Clean Air Amendments of 1970, the Clean Water Act of 1972, and the Endangered Species Act of 1973, among others.

Unlike those later-enacted laws, however, NEPA imposes no substantive environmental obligations or restrictions. NEPA is a purely procedural statute that, as relevant here, simply requires an agency to prepare an EIS—in essence, a report. Importantly, NEPA does not require the agency to weigh environmental consequences in any particular way. Rather, an agency may weigh environmental consequences as the agency reasonably sees fit under its governing statute and any relevant substantive environmental laws.

Simply stated, NEPA is a procedural cross-check, not a substantive roadblock. The goal of the law is to inform agency decisionmaking, not to paralyze it.

In this case, the U. S. Surface Transportation Board considered a proposal by a group of seven Utah counties for the construction and operation of an approximately 88-mile railroad line in northeastern Utah. Under federal law, the Board determines whether to approve construction of new railroad lines. The railroad line here would connect Utah’s oil-rich Uinta Basin—a rural territory roughly the size of the State of Maryland—to the national rail network. By doing so, the new railroad line would facilitate the transportation of crude oil from Utah to refineries in Louisiana, Texas, and elsewhere. And the project would bring significant economic development and jobs to the isolated Uinta Basin by better connecting the Basin to the national economy.

For that proposed 88-mile Utah railroad line, the Board prepared an extraordinarily lengthy EIS, spanning more than 3,600 pages of environmental analysis. The Board’s EIS addressed the environmental effects of the railroad line. But the U. S. Court of Appeals for the D. C. Circuit nonetheless faulted the EIS for not sufficiently considering the environmental effects of projects separate from the railroad line itself—primarily, the environmental effects that could ensue from (i) increased oil drilling upstream in the Uinta Basin and (ii) increased oil refining downstream along the Gulf Coast of Louisiana and Texas.

On that basis, the D. C. Circuit vacated the Board’s EIS and the Board’s approval of the 88-mile railroad line. As a result, construction still has not begun even though the Board approved the project back in December 2021.

We reverse. First, the D. C. Circuit did not afford the Board the substantial judicial deference required in NEPA cases. Second, the D. C. Circuit ordered the Board to address the environmental effects of projects separate intime or place from the construction and operation of the railroad line. But NEPA requires agencies to focus on the environmental effects of the project at issue. Under NEPA, the Board’s EIS did not need to address the environmental effects of upstream oil drilling or downstream oil refining. Rather, it needed to address only the effects of the 88-milerailroad line. And the Board’s EIS did so.

 

Hans Bader

Hans Bader

Hans Bader practices law in Washington, D.C. After studying economics and history at the University of Virginia and law at Harvard, he practiced civil-rights, international-trade, and constitutional law. He also once worked in the Education Department. Hans writes for CNSNews.com and has appeared on C-SPAN’s “Washington Journal.” Contact him at hfb138@yahoo.com

Comments

For your convenience, you may leave commments below using Disqus. If Disqus is not appearing for you, please disable AdBlock to leave a comment.